Bowthorpe House are pleased to report a great start to the ground works on our latest site.  Taking advantage of the fine weather conditions, full strip of the vegetation and subsequent top soil has been achieved in a week which has positioned us ahead of schedule.

View from the South West corner of the site.

Removal of top soil is well underway exporting it to a hired field near, with over 160 lorry loads already removed. Over the coming days this will be completed, leaving a clear site for all foundations to be dug out.

Plot 1 Foundation Progress

The foundations for Plot 1 have been already excavated and concreted. The plan is to work around the site in an anticlockwise direction completing all foundations shortly.

We will shortly present selective plots to the market however we have already received serious interest.