Full Steam Ahead
With the torrential rainfall far behind us and heatwave conditions this week, its all systems go at The Meadows. We lost 7 site days due to the poor weather last month, however as we were ahead of programme, we have been able to pick up accordingly.
We have now completed the roof trusses to plots 5, 8 & 9, although its fair to say the trusses to plots 8 & 9 took longer than we would have liked. However the site team did an amazing job delivering what are very complex designs.


Plots 6 & 7 are to receive their roof trusses this week, plot 4 is now up to wall plate and plots 3, 2 & 1 are very close behind in the course of second lift.