Tag: NewBuild

Fitting Out & External Work

In the last month, progress has been maintained well on site. The programme has altered bring forward and accommodate the external works to now match planned occupation of Plot 2,3,4 & 5. All plots will be occupied the end of March 2022. Within the last month, we have welcomed our new owners to plot […]

Read more
Fitting Out and External Works

Its been a very busy period on site at Bellamy Farm. All units are now watertight with the last of the bi folds being glazed to plot 5. Plots 1 has completed and we look forward to welcoming the new owners tomorrow. For the rest of the site, focus has turned to fitting out and […]

Read more
All Plots SOLD

We are pleased to confirm all plots are now sold on our Bellamy Farm Development in North Scarle. Dependant on the time of sale, all purchasers have been able to chose alterations to suite them and their new home. We look forward to welcoming them to their new home and community in due course.

Read more
Roofing & Fitting Out

Progress has been made on all fronts with the site team working well and committed to the programme. Windows have caused us some issues with poor performance the manufacturer, this has impacted to plots 1 & 2 but not the rest of the properties. Focus has therefore been made to drive the first fix […]

Read more
Roofs And More Brick & Blockwork

We are pleased to report great progress in the last month. One of the brick types being used was proving hard to source, the delivery promised for the 18th Oct looked to be in question, however with a few phone calls, the supplier pulled through and delivery was made as promised. We now have all […]

Read more
Roofing & 2nd/3rd Lift Brickwork

Progress continues on site, albeit slightly behind programme. We are currently 2/3 weeks behind owing to scaffold availability, scaffold already on site is being used creatively and is moving to plots to minimise delays and maintain as much pace as we can provide. Plot 2 is slightly ahead of programme and can allow 1st fix […]

Read more
First Lift Brick & Block Progress

The past month has provided good weather with just the occasional spell of rain to assist the site team’s progress. More significant milestones have been achieved in that the superstructures are taking shape in Plots 1 & 2 which really shows the generous plot sizes and room dimensions. Plots 3,4 & 5 are now up […]

Read more
Plot 1

We are delighted to confirm the sale subject to contract of plot 1. 2020 has been a challenging year for all of us. With two lockdowns under our belt, we have been able to determine what is important to us. The health and wellbeing of ourselves and our family are uppermost but also what we […]

Read more
Full Steam Ahead

With the torrential rainfall far behind us and heatwave conditions this week, its all systems go at The Meadows. We lost 7 site days due to the poor weather last month, however as we were ahead of programme, we have been able to pick up accordingly. We have now completed the roof trusses to plots […]

Read more
Plot 8 – The Chestnut SOLD

After recently releasing plots 1, 5 and 8 to the market, we quickly received a lot of interest. We are delighted to confirm Plot 8 has now been sold subject to contract. We look forward to working with the lovely couple and our agents to ensure the sale happens as seamlessly as possible.

Read more